Friday, November 30, 2007

Day 4 1/2

We thought that Friday would be an off day for the workers, but they began before 7:00, when the concrete trucks arrived. Jeff told us they wanted to lay the pad for the garage today to give it time to cure. With the leftover they extended the footing for one side of the original driveway and poured a footing for the front retaining wall, as the photos show.


By the way, today's work was overtime for the boys, so I am sure they welcomed it.

This was one busy week for the crews. We had no idea they would be this far along at the end of the first week.


Monday they pour the front sidewalk.




Thursday, November 29, 2007

Day 4

Looks like they did a lot today. Exciting! Here's some photos.




Wednesday, November 28, 2007

Day 3: Major Changes

Well, Day 3 is over now. It began this morning at about 6:05, long before sunup, when the crew arrived and revved up the diesel engines and started moving earth. When those machines back up, of course the warning signal goes off, so between the diesel engines and warning signals, and the high-intensity lights, I don't know how our neighbors in the five apartments were able to sleep. I got home about 4:45 in time to take some photos in the fading daylight. It was overcast anyway, so it was darker than it would normally be. Here are some photos:

A rectangle trench was dug in the backyard and the footings were poured for the foundation and retaining walls. The concrete was still wet and water was standing on it.

In the second photo, taken from the alley, you can see part of the footing, but you can also see the spray paint that marks the phone cable. AT&T came by today to repair the cable, but for now it lies on top of the ground, and it makes an end around the garage so that it won't be covered up by the concrete pad that will be poured.

The next one shows the splice in the alley, where the new cable is spliced onto the cable that comes up from the ground in the alley. The ground had worn away over the years until the phone cable was exposed.


The next photo shows the footings for the new retaining walls on each side of the original driveway:


A final picture--here is a shot of the equipment parked in the yard on the Glenview side, with a big pile of excavated dirt:


The forms out front look set, so I think that Thursday the front sidewalk will be poured. I bet there will be enough changes to post to this blog tomorrow.

Stealing the Internet

This is just a short post. We were without phone service all of Tuesday, as the lines were disconnected to allow for earth-moving work. When the wires were spliced together, they must have been spliced wrong. About 12 feet of phone cable lay on top of the earth yesterday, spliced in two places and tears in two more. The phones didn't work; couldn't even get a dial tone. Of course, neither would our DSL. Last night late, I was using our laptop to do word-processing, knowing I couldn't connect, when all of a sudden a box opened and Kelly broke in with a chat. Lordy, lordy, it's a miracle, I thought. We chatted for awhile, all the time I'm trying to figure out how, when it dawns on me. Someone next door must have wireless internet, and our laptop detected their unsecured wireless internet. The connection was low, but it worked, and so I did some internet surfing after finishing the chat.

So I say thanks to Kelly next door, or Charles in the garage apartment, or one of the other three in the front apartments, for allowing me to use their internet connection!

Our service is supposed to be repaired today by AT&T. If they send us a bill, I am passing it on to Jeff Neal.